Security of payment timeframes in Queensland: a dated reference

In Queensland, a respondent has 15 business days to give a payment schedule. Payment falls due 10 business days after the claim if the contract is silent, capped at 15 business days for commercial building contracts and 25 for subcontracts. Adjudication applications run 20 or 30 business days depending on what came back.

Reviewed
Jurisdiction
Queensland, Australia
Reading time
5 min
For
Anyone tracking a claim, a schedule or an adjudication deadline in Queensland

This is the whole regime as a table, current as at 5 August 2026. Timeframes come from the Building Industry Fairness (Security of Payment) Act 2017 (Qld) except the payment-due caps, which sit in the Queensland Building and Construction Commission Act 1991 (Qld). Your contract can shorten some of these. It cannot lengthen the ones marked as caps.

The timeframes

Queensland security-of-payment timeframes, reviewed 5 August 2026
StepWho actsTime allowedSource
Give a progress payment claimClaimantThe longer of the period under the contract, or 6 months after the work was last carried outBIF Act s 75
Give a final payment claimClaimantThe longest of: the contract period; 28 days after the last defects liability period ends; 6 months after all work is complete; 6 months after the last related goods and servicesBIF Act s 75
Give a payment scheduleRespondentThe earlier of the contract period, or 15 business days after the claim is givenBIF Act s 76
Progress payment falls due — contract silentRespondent10 business days after the claim is givenBIF Act s 73
Progress payment falls due — commercial building contract (cap)RespondentMaximum 15 business days after the claim. A longer term is void.QBCC Act s 67U
Progress payment falls due — subcontract (cap)RespondentMaximum 25 business days after the claim. A longer term is void.QBCC Act s 67W
Adjudication — schedule was for less than claimedClaimant30 business days after the payment schedule is givenBIF Act s 79
Adjudication — no schedule given and not paid in fullClaimant30 business days after the later of the due date, or the last day a schedule could have been givenBIF Act s 79
Adjudication — schedule given but scheduled amount not paidClaimant20 business days after the due date for paymentBIF Act s 79
Adjudication response — standard claimRespondent10 business days after receiving the applicationBIF Act s 82
Adjudication response — complex claimRespondent15 business days after receiving the applicationBIF Act s 82
Adjudication response — no payment schedule was givenRespondentNone. A respondent who gave no payment schedule may not give an adjudication response.BIF Act s 82

Source: BIF Act ss 73, 75, 76, 79, 82; Queensland Building and Construction Commission Act 1991 (Qld) ss 67U, 67W

Why there are three adjudication windows

The window you are in depends on what the respondent did, not on what you claimed. Getting this wrong is fatal — an application made outside the window cannot be heard, however good the underlying claim is.

  1. 1.They scheduled less than you claimed. You are disputing the amount. 30 business days, running from the day the schedule was given — not from the due date for payment.
  2. 2.They gave a schedule and then did not pay the scheduled amount. You are not disputing anything; they agreed the number and did not pay it. 20 business days from the due date.
  3. 3.They gave nothing at all. 30 business days from the later of the due date for payment, or the last day on which a schedule could have been given.

What your contract can and cannot change

Contractual variation of statutory timeframes
TimeframeCan the contract change it?
Payment schedule deadlineIt can require a schedule sooner than 15 business days. It cannot allow longer.
Due date for paymentIt can require payment sooner. A term allowing longer than the QBCC Act cap is void, and the statutory position applies instead.
Payment claim windowIt can give you longer than six months. It cannot cut the six months short.
Adjudication windowsNo. These are statutory and cannot be contracted out of.

Source: Queensland Building and Construction Commission Act 1991 (Qld) ss 67U, 67W; BIF Act ch 3