Resources · Queensland security of payment
Getting paid is a paperwork problem.
Almost every subcontractor who loses money on a Queensland job had the entitlement and missed the document or the deadline. These are the deadlines and the documents, written plainly, with the section numbers so you can check us.
Reviewed 5 August 2026 against the Building Industry Fairness (Security of Payment) Act 2017 (Qld) and the QBCC Act 1991. General information, not legal advice.
Guides
Subcontractors and head contractors claiming progress payments in Queensland · 6 min read
What must a payment claim contain under the BIF Act (Qld)?
Under section 68 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), a payment claim must be a written document that identifies the construction work or related goods and services it relates to, states the amount claimed, and requests payment of that amount. It no longer has to say it is made under the Act.
Read it →
Anyone tracking a claim, a schedule or an adjudication deadline in Queensland · 5 min read
Security of payment timeframes in Queensland: a dated reference
In Queensland, a respondent has 15 business days to give a payment schedule. Payment falls due 10 business days after the claim if the contract is silent, capped at 15 business days for commercial building contracts and 25 for subcontracts. Adjudication applications run 20 or 30 business days depending on what came back.
Read it →
Subcontractors who have had a claim certified down · 7 min read
What is a payment schedule, and what to do when it comes back short
A payment schedule is the respondent's written response to a payment claim. It must identify the claim, state the amount they propose to pay, and — if that is less than claimed — say why, including their reasons for withholding. In Queensland they have 15 business days. If it comes back short you have 30 business days to apply for adjudication.
Read it →
Subcontractors and builders claiming variations · 8 min read
How to write a variation claim that gets paid
A variation claim gets paid when it proves four things separately: that an instruction was given, that the instruction changed the contracted scope, what the change is worth built up from your contract rates, and what it did to the programme. Claims fail on the first of those far more often than on the price.
Read it →
Subcontractors managing programme risk on Queensland projects · 7 min read
Extension of time notices in Queensland subcontracts
An extension of time notice tells the other party that a delay event has occurred, when it started, what caused it, and what effect it has on the date for practical completion. In most Queensland subcontracts the notice period is a condition precedent: give it late and the entitlement is lost, however genuine the delay.
Read it →
Comparisons
The honest version of “why not just use…”
Each of these says what the other thing is genuinely better at, in the same size type. If that section were ever empty the page would not be worth publishing.
vs
ChatGPT and other chat assistants
ChatGPT is better than Lunar8Ops at open-ended writing and reasoning from a blank page. It cannot hold your rates permanently, guarantee it will not contradict a price you have certified, act on work arriving in your inbox, or route a draft to the person who must sign it. Those four are the product.
Compare →
vs
hiring a freelance bid writer
A good bid writer brings strategy, win themes and an outsider's read of the evaluation criteria — Lunar8Ops does none of that. What it does is the first draft from your own past submissions, the rate accuracy, and the claims and notices between tenders. Most subcontractors who use both use the writer on fewer, bigger bids.
Compare →
vs
simPRO, AroFlo, Procore and other job-management systems
No. simPRO, AroFlo, Procore and similar systems own the job, the schedule, the register and the ledger, and they price a job once someone enters the line items. None of them writes the tender response, the prequalification answer, the variation claim narrative or the extension-of-time notice, because they were not built to.
Compare →
Want this applied to a tender that is open right now?
Tell us your company name. Within one business day you get one page: a live package, and the questions in it where your published evidence does not cover the answer, with the closing date at the top. You send us nothing.