What is a payment schedule, and what to do when it comes back short

A payment schedule is the respondent's written response to a payment claim. It must identify the claim, state the amount they propose to pay, and — if that is less than claimed — say why, including their reasons for withholding. In Queensland they have 15 business days. If it comes back short you have 30 business days to apply for adjudication.

Reviewed
Jurisdiction
Queensland, Australia
Reading time
7 min
For
Subcontractors who have had a claim certified down

Current as at 5 August 2026, under the Building Industry Fairness (Security of Payment) Act 2017 (Qld).

What a payment schedule must contain

Required contents of a payment schedule
RequirementWhy it matters to you
It identifies the payment claim it responds toA schedule that does not identify the claim may not be a schedule at all — which puts the respondent in the “gave nothing” category.
It states the amount the respondent proposes to payThis is the “scheduled amount”. If they do not pay it, that is a different and shorter adjudication window than disputing it.
If the scheduled amount is less than claimed, it states whyIncluding the reasons for withholding payment. This is the part that constrains them later.

Source: BIF Act s 69

Read it properly before you react

  1. 1.Find the scheduled amount and diarise the due date. If they scheduled an amount and then do not pay it, you have 20 business days from the due date — the shortest window in the Act.
  2. 2.List every reason they gave, verbatim. That list is the entire universe of arguments available to them later.
  3. 3.Match each reason to a line in your claim. Reasons that do not attach to a specific line are weak, and reasons attached to lines you can evidence are the ones to answer first.
  4. 4.Separate valuation disputes from entitlement disputes. “We say that variation is worth $4,000, not $9,000” is a valuation argument you win with rates and measurement. “There was no instruction, so there is no variation” is an entitlement argument you win with correspondence.
  5. 5.Check what they did not dispute. Anything unmentioned is effectively conceded for that claim.

Your windows, and which one you are in

Adjudication window by what the respondent did
What happenedYour windowRuns from
Schedule for less than you claimed30 business daysThe day the payment schedule was given
Schedule given, scheduled amount not paid20 business daysThe due date for payment
No schedule, not paid in full30 business daysThe later of the due date, or the last day a schedule could have been given

Source: BIF Act s 79

Before you spend money on adjudication

Adjudication is fast and comparatively cheap, but it is not free and it costs you a relationship you may want next year. Two questions worth answering honestly first.

Can you evidence the disputed lines today? Not “could we find it” — can you produce, this week, the instruction, the marked-up drawing, the site diary entry, the dayworks sheet signed by someone on their side? An adjudicator decides on the material in front of them within a very short timetable. A strong entitlement with no contemporaneous record loses to a weak defence with one.

Is the gap valuation or entitlement? Valuation gaps often close with a properly built claim and a conversation. Entitlement gaps rarely do, because someone has already decided you were not entitled, and no amount of rebuilding the claim changes their mind.

Sources